High School ISL « Hillside » Expansion
Building owner
Ministry of Finance / International School of Luxembourg ISL
Location
Luxembourg
With an increase in demand for students, Paul Wurth Geprolux took the project on to expand the school by adding 12 classrooms. Paul Wurth was responsible for the engineering and realisation of this building with prefabricated steel-concrete elements. This allowed a record 4-months construction period. The achieved a level of quality is identical to traditional buildings which are constructed on site. .
Key figures
Built volume
9.500 m3
Built surface
2.700 m2
Project duration
(10 Months) 2007
Construction period
4 Months
Our missions
- Project preparation
- Project management
- Design coordination
- Permitting
- Execution design
- Call for tenders
- Contract management
- Construction site management
- Works coordination
- Commissioning
Design team
Architect
Lucien Zbiorczyk