School for the 2nd chance
After 7 years of utilization of the building by the « Neien Lycée » which moved to Mersch, Paul Wurth Geprolux challenged itself to propose a new scholar concept for teachers regarding spaces matching their needs.
The existing premises were developed and transformed in order to host a scholar universe with a more practical and professional orientation.
Key figures
Built volume
12.000 m3
Built surface
3.500 m2
Project duration
(6 months) 2012
Construction period
5 months
Utilization duration
2012- 2019
Our missions
- Project scope
- Project management
- Design coordination/ Permitting
- Execution design
- Budget management
- Construction site management / Coordination of the works
- Execution of the works
- Quality management
- Reception / Commissioning
- Financing services
- Facility management
Our services
Design team
General planner
Paul Wurth Geprolux
To discover
also
A new project?