LUXLAIT – Demolition of the old factory

Building owner

Luxlait agricultural association

Location

Luxembourg

In 2005, Luxlait sold its industrial wasteland in the heart of Luxembourg city. In the sales contract, Luxlait committed to organize, implement and finance the suspension of their activities and the demolition of the existing plant. This mixed site, offices and factory, encountered many complexities in the dismantling, including asbestos problems, administrative permits, sale of steel products, partial remediation of soil, etc..

Key figures

Built volume

200.000 m3

Built surface

35.000 m2

Project duration

2009 – 2010

Construction period

2010

Our missions

  • Project preparation
  • Project management
  • Permitting
  • Sanitation studies
  • demolition studies
  • Call for tenders
  • Budget management
  • Contract management
  • Construction management
  • Works coordination
  • Commissioning

Design team

General Planner

Paul Wurth Geprolux

To discover