High School for sports (“Sportlycée”)
Building owner
Ministry of the sustainable development and infrastructures / Administration of public buildings
Location
Luxembourg
The scholar building, proposing 18 classrooms for approximately 400 students, should have been built in record time of only 12 months according to the needs of the Sportlycée.
The constructive concept (mix steel + concrete) is based on some main criteria :
1.efficient building regarding energy consumption and sustainability, and
2.construction costs optimization and quickness of execution
The energy concept follows the recommendations of the office Basler + Partner.
Key figures
Built volume
17.500 m3
Built surface
5.300 m2
Project duration
(14 months) 2011 - 2012
Construction period
(10 months) 2011 - 2012
Our missions
- Project Management
- Execution design
- General contractor
- Coordination and construction management
- Quality control and conformity of the works
Our services
Design team
Architect
Beiler + François Architectes
Engineer
Paul Wurth Geprolux
To discover
also
A new project?