ArcelorMittal – Office building

Building owner

ArcelorMittal Luxembourg Real Estate

Location

Esch / Alzette

The refrigeration machines of the AMOB building worked with R 22 as refrigerant and were no longer allowed to be exploited beyond the year 2009. Thus the refrigeration unit has been completely rebuilt with the installation of 4 new refrigeration compressors with magnetic suspension, running R134a and 2 hybrid cooling towers on the roof.

Key figures

Cooling capacity

1.200 kW

Project duration

2007-2010

Construction time

2008-2009

Our missions

  • Feasibility study
  • Technical concept
  • Permitting
  • Preliminary design
  • Detail design
  • Call for tenders
  • Construction management
  • Commissioning
  • Follow-up post-mortem