The existing plant processing steel products is equipped with several cranes which can lift and carry very heavy loads. It is within this context that Paul Wurth Geprolux has organized the rebuilding of the tracks (worn over time by the crane movements) and partial columns of the hall (weakened by differential settlements of foundations).

Key figures

Project duration

2007

Construction period

2007

Our missions

  • Feasability study
  • Preliminary design
  • Call for tenders
  • Budget management
  • Construction management
  • Commissioning

Design team

General planner

Paul Wurth Geprolux in collaboration with Klaus-Dieter Gorges