Paul Wurth Geprolux has been entrusted for the management of the guarantees and latent defects for the period beginning after the construction of the 4th extension of the Court. In the frame of this mission the responsibilities of the locator, having their origins in the contract between the Grand Duchy of Luxembourg and the Court, were managed as well. A multitude of latent defects, touching various and severe technical fields as for example water tightness, structures vibrations, disorders due the effects of the weather, were taken into consideration and processed.
Key figures
Project duration
2010 – ongoing
Construction period
2010 – ongoing
Our missions
- Preparation of the project
- Clarification of the responsibilities
- Project management
- Contract management
- Coordination of the design
- Coordination of the expertises
- Coordination of the works
- Reporting
Design team
Architect
Dominique Perrault Architecture / APF
Civil Engineer
Schroeder & A. / IncA
Technical Engineer
Felgen & A. / RMC / Jean Schmit Engineer