Extension of the Carlex Industrial Factory

Building owner

Carlex Glass Luxembourg

Location

Grevenmacher

Carlex aims to modernize its production line in Luxembourg with the implementation of a new process furnace. The client has contracted Paul Wurth Geprolux to execute the overall project management of the extension of its existing factory in order to shelter this new line, a storage of raw glass and transformers. Paul Wurth Geprolux’s objective is to design a building according to the needs of the customer’s processes, to improve the construction concept in order to guarantee the best return on investment and to perform the works according to the production schedule.

Key figures

Gross volume

30.000 m3

Gross surface

3.500 m2

Project duration

06.2016-10.2017

Our missions

  • Design Team:
    • Architecture, Civil Engineering and Structures, Technical Engineering ( Electricity, HVAC and Sanitary)
  • Coordination of the design team
  • Authorisations
  • Call for tenders
  • Project Management:
  • Coordination
  • Budget Management
  • Scheduling
  • Construction Site Supervision

Design team

General planner

Paul Wurth Geprolux