Wastewater treatment plant LUXLAIT
The new dairy plant of the agricultural association LUXLAIT is designed for 116 Mio kg/year. According to EC directives, large dairy plants need to plan their own wastewater treatment.
However, the scheduled start-up of the waste water treatment plant was 6 months after than the start-up of the dairy plant. This meant that an intermediate solution had to be designed for the waste water treatment, in association with the urban water clarification syndicates.
Key figures
Capacity (equivalent citizen)
5.400 EH
Wastewater massflow
600 m3/d
Project duration
2009-2010
Our missions
- Project preparation
- Studies coordination
- Call of tenders
- Permitting
- Budget management
- Construction organization and coordination