HUSKY – Factories and Warehouses
Client since 1984 for all 4 buildings on its Luxembourgish site, Husky is a loyal customer. The original plant and the three extensions are technically very complex structures through their ventilation systems that need to create a special atmosphere, necessary for the production of mechanical technologies which are very sensitive to dust.
Key figures
Built volume
~150.000 m3
Built surface
21.000 m2
Project duration
1984 – 2001
Duration of the last site
1998 – 2001
Our missions
- Project scope
- Project management
- Preliminary design
- Permitting
- Execution design
- Call for tenders
- Budget management
- Contract management
- Construction management
- Works coordination
- Construction works
- Commissioning
Our services
Design team
General planner
Paul Wurth Geprolux
To discover
also
A new project?