The refurbishment and expansion of the 100-bed rehabilitation center was requiring a considerable logistical coordination and a high level of hygienic cleanliness. Paul Wurth was required to provide a temporary facility during the project because the Red Cross Center in Colpach was held operational during the works.
Key figures
Built volume
46.500 m3
Built surface
11.000 m2
Project duration
2004 - 2009
Construction period
2005 – 2009
Our missions
- Technical assistance to building owner
- Technical audit
- Cost management
- Schedule management
- Coordination of asbestos removal
- Site management