This new school building construction, managed by Paul Wurth Geprolux, contains classrooms, a sportshall, a library, bathrooms, art and music workshops, 2 playgrounds and 2 outside parking areas. It is important to point out that the building meets new environmental standards and get an environmental certification (DGNB) as well.
The project was realised in respecting the time frame and the budget envelope.
Key figures
Gross volume
60.000 m3
Gross surface
18.000 m2
Project duration
2009-2013
Our missions
- Project scope
- architectural contest
- Project preparation
- Project management
- Design coordination
- Permitting
- Budget management/Controlling
- Contract management
- Construction site management
- Commissioning
- Organisation of moving
Design team
Architect
Arco Architecture Company
Civil Engineer
InCA
Technical Engineer
Betic